Pershing & Silver Street Improvements
The Pershing/Silver Waterline Replacement Project is a planned infrastructure improvement that will upgrade water lines along portions of Pershing Street and Silver Street. By replacing aging water mains and related equipment, the project aims to improve system reliability, support fire protection, reduce maintenance needs, and help provide more dependable water service for area residents.
| UPDATE: 11/9/2026 | Pershing & Silver Street Improvements - Colonias CIF-6441 |
| PURPOSE |
The Pershing/Silver project is a waterline replacement and improvement project intended to replace aging water infrastructure along portions of Pershing Street and Silver Street in Truth or Consequences. The project includes installation of new water mains and associated water-system components such as valves and hydrants.
|
| TIMELINE |
The Pershing/Silver Waterline Replacement Project began with a Notice to Proceed issued on June 1, 2026, followed by a project kickoff meeting on June 9, 2026. The design process has progressed through several review stages, including a 30% design review on July 22 and a 60% design review on September 15. The project team anticipated submitting the 90% design package in October 2026, with final design completion targeted for October 22, 2026. Originally, the project was expected to be advertised for construction bids in November 2026, although that schedule was later expected to shift to January due to commission meeting timing and other administrative considerations. The project is currently awaiting an additional funding allocation of approximately $1 million. As a result, bidding activities have been placed on hold and regular progress meetings have been suspended until the funding and review process advances.
|
| SCOPE | Pershing Street: approximately 3,482 linear feet of waterline replacement from East 9th Avenue to New School Road. Silver Street: approximately 1,793 linear feet of waterline replacement from East 3rd Avenue to East 8th Avenue. Total waterline replacement length is approximately 5,275 linear feet (about one mile). |
| BENEFITS |
The Pershing/Silver waterline replacement project is expected to provide several long-term benefits for the community. By replacing aging water infrastructure, the project aims to improve the reliability of the city's water distribution system and reduce the likelihood of water main breaks and related service disruptions. Planned upgrades to water mains, valves, hydrants, and service connections are also expected to enhance fire protection capabilities and improve the system's overall performance. In addition, the improvements should make future maintenance more efficient, helping to support the long-term operation and reliability of the community's water system.
|
| DISRUPTIONS |
Residents may experience temporary disruptions during construction, including lane closures, traffic delays, construction noise, and localized sidewalk or pavement repairs. Water service interruptions may also occur at times when new waterlines are connected to the existing system. To help reduce these impacts, project planners are reviewing utility conflicts, coordinating construction activities, and evaluating sidewalk restoration methods to minimize the extent of repairs required.
|
| MITIGATION STRATEGIES |
To help minimize disruptions during construction, project planners are working closely with gas companies and other utility providers to identify and address potential conflicts before work begins. The construction schedule will be carefully sequenced to reduce interference between utility installations and other project activities. The team is also considering limiting sidewalk work to saw cuts and localized repairs rather than replacing entire sections of sidewalk, which could reduce costs and lessen impacts on nearby residents and businesses. In addition, further reviews of existing utilities will be conducted during the final planning stages to help identify and resolve conflicts before construction starts.
|
| FUNDING |
Funding is being provided in part through Colonias Infrastructure funds. Additional funding is to be determined.
|
| TOTAL FUNDING FOR PLANNING, DESIGN, CONSTRUCTION & CONSTRUCTION MANAGEMENT | $ To be determined. |
| APPLICATION ENGINGEER | Not applicable. |
| ENGINEER | Wilson & Company |
| CONTRACTORS | To be determined. |
| RESOURCES | None at this time. |